Kathmandu: The Nagdhunga tunnel route is awaiting a breakthrough as only 73.60 metres is left to work. Breakthrough in the evacuation tunnel which is 2.55 kilomeres long was already completed in August 2023. So far, 51 per cent of the concrete's work inside the tunnel is completed and the workers are not preparing to fix…